Arbitral Award Can't Be Interfered With Just Because Another Interpretation Of Contract Is Possible : Supreme Court
Why Courts Cannot Rewrite Contracts: Supreme Court Reaffirms Limits on Interfering With Arbitral Awards
Meta Description: The Supreme Court has ruled that courts cannot interfere with an arbitral award merely because another interpretation of the contract is possible. This detailed article explains the NHAI vs HCC judgment, its legal reasoning, and its impact on arbitration law in India.
Table of Contents
- Introduction
- Background of the Dispute
- How the Arbitration Began
- The Claims Before the Arbitral Tribunal
- What the Arbitral Tribunal Decided
- Challenge Before the Delhi High Court
- Appeal to the Supreme Court
- Arguments of NHAI
- Arguments of the Contractor
- What the Supreme Court Examined
- Key Observations of the Supreme Court
- Why Courts Must Respect Arbitral Interpretation
- Impact on Arbitration Law in India
- What This Means for Contractors and Government Bodies
- Conclusion
Introduction
One of the biggest reasons businesses choose arbitration is finality. If courts begin to re-examine every contract clause and every interpretation, arbitration would lose its very purpose. In a significant judgment delivered on May 7, 2024, the Supreme Court once again made it clear that courts are not meant to sit as appellate authorities over arbitral awards.
The Court held that an arbitral award cannot be interfered with simply because another interpretation of the contract is possible. This ruling came in the case between the National Highways Authority of India and Meissners Hindustan Construction Company Limited and carries important consequences for arbitration in India.
Background of the Dispute
The dispute arose from a major infrastructure project involving the construction of the Allahabad Bypass on National Highway. In 2004, NHAI awarded the contract to Hindustan Construction Company for building a stretch of road between kilometer 158 and kilometer 198. The total value of the project ran into several hundred crores of rupees.
As often happens in long infrastructure projects, disagreements soon developed regarding payments, additional costs, and interpretation of contractual clauses.
How the Arbitration Began
When negotiations failed to resolve these disputes, the matter was referred to arbitration in accordance with the contract. A three-member Arbitral Tribunal was constituted to decide the claims raised by the contractor.
The Claims Before the Arbitral Tribunal
The contractor raised three major claims. First, it sought reimbursement for additional expenses caused by an increase in royalty rates on construction materials. Second, it claimed payment for embankment work which, according to the contractor, had not been properly compensated. Third, it sought reimbursement for increased forest transit fees.
What the Arbitral Tribunal Decided
After examining the contract documents, evidence, and technical material, the Tribunal allowed all three claims. It awarded substantial sums to the contractor along with interest. On the second claim relating to embankment work, two expert members of the Tribunal ruled in favor of the contractor, while one member dissented.
Challenge Before the Delhi High Court
NHAI challenged the arbitral award under Section 34 of the Arbitration and Conciliation Act before the Delhi High Court. However, the Single Judge upheld the award. A further appeal under Section 37 was also dismissed by the Division Bench of the High Court.
Unhappy with these decisions, NHAI approached the Supreme Court.
Appeal to the Supreme Court
Before the Supreme Court, NHAI argued that the Tribunal and the High Court had misinterpreted the contract clauses relating to price adjustment and additional payments.
Arguments of NHAI
NHAI claimed that the contract already contained a formula to adjust prices based on the Wholesale Price Index and that no separate payment should have been granted. It also argued that the clause dealing with embankment work had been wrongly interpreted and that the contractor was not entitled to separate payment for it.
According to NHAI, the courts should have corrected these errors.
Arguments of the Contractor
The contractor responded by pointing out that courts have very limited power to interfere with arbitral awards. It argued that the Tribunal’s interpretation was a possible and reasonable view and that courts cannot replace the arbitrator’s interpretation with their own.
What the Supreme Court Examined
The Supreme Court noted that three forums had already agreed on the same conclusion: the Arbitral Tribunal, the Single Judge, and the Division Bench. The Court emphasized that it was not sitting as a court of appeal over the arbitrator’s decision.
The Court also referred to earlier judgments which clearly state that interference with arbitral awards is permitted only in very exceptional cases, such as when the award violates public policy or suffers from patent illegality.
Key Observations of the Supreme Court
The Supreme Court made it clear that interpretation of a contract is primarily the domain of the arbitrator. If the arbitrator has taken a plausible view after examining the material, courts cannot interfere merely because another interpretation is also possible.
The Court also noted that when technical experts form the majority in an arbitral tribunal, their opinion deserves even greater respect.
Why Courts Must Respect Arbitral Interpretation
If courts start reinterpreting contracts in arbitration cases, arbitration would become meaningless. The whole purpose of choosing arbitration is to avoid long court battles and to get a final and binding decision from a specialized forum.
This judgment reinforces the idea that courts are supervisors, not reviewers, of arbitral awards.
Impact on Arbitration Law in India
This ruling strengthens India’s image as an arbitration-friendly jurisdiction. It sends a clear message that arbitral awards will not be casually disturbed and that parties must live with the arbitrator’s interpretation unless it is completely unreasonable or illegal.
What This Means for Contractors and Government Bodies
For contractors, this judgment offers greater certainty that awards in their favor will not be easily overturned. For government bodies, it is a reminder that once they agree to arbitration, they must respect the outcome even if they disagree with the reasoning.
Conclusion
The Supreme Court’s judgment in the NHAI vs Hindustan Construction Company case is a strong reaffirmation of the principle that courts cannot rewrite contracts through arbitration challenges.
By refusing to interfere merely because another interpretation was possible, the Court has protected the sanctity of arbitration and reinforced the rule that arbitral awards must be respected, not re-argued.
This decision will serve as an important precedent in ensuring that arbitration in India remains efficient, final, and credible.

Comments
Post a Comment